Project Margin Variance Report – Requirements Specification

Version: 1.0
Owner: Regional Finance Director
Prepared by: Data Engineering


1. Purpose

The purpose of this report is to provide clear and consistent visibility of margin performance across all active projects, comparing the originally approved bid margin with the latest forecast outturn margin. The report will support financial oversight, early risk identification, and commercial performance management at project, PRU, and regional levels.


2. Objectives

  • Allow Finance to identify projects with margin erosion or variance from approved bid assumptions.
  • Provide a structured view of bid vs forecast values and margins.
  • Support monthly financial reviews, period-end accounts, and PRU-level consolidation.
  • Enable investigation of the drivers of margin change.
  • Provide consistent, auditable figures aligned with Data Warehouse definitions.

3. Primary User Story

As a Regional Finance Director,
I need to compare the current forecast outturn margin for each project against the original bid margin,
so that I can identify margin slippage early, investigate causes, and take corrective action where needed.


4. Stakeholders

StakeholderRole
Regional Finance DirectorSponsor, primary consumer
PRU Managers / Programme LeadsReview project performance
Project ManagersProvide updated forecasts
Financial Accounts TeamUse outputs for month-end analysis
Data EngineeringProduce and maintain the report/data pipeline
PMO (if applicable)Monitor delivery performance and RAG status

5. Scope

In Scope

  • All active, planned, and recently closed customer projects.
  • Bid (baseline) and forecast (current) commercial values.
  • Margin and value variance calculations.
  • Reporting at project and PRU level.

Out of Scope (initially)

  • Earned value or % complete metrics.
  • Scenario or sensitivity analysis.
  • Time-phased forecasting.
  • Commentary capture (may be considered later).

6. Data Requirements

6.1 Core Data Fields

The following fields are required to deliver the minimum viable product (MVP):

FieldDescription
Project IDUnique project identifier
Project NameFull name of the project
PRUProgramme Reporting Unit / Cost Centre
Bid Value (£)Revenue or total contract value at bid approval
Current Value (£)Latest forecast revenue/contract value
Bid Margin (%)Margin approved at contract/bid stage
Current Outturn Margin (%)Latest forecast margin
Start DateProject commencement date
Expected Completion DateCurrent projected finish date

6.2 Derived Fields

These fields will be calculated within the report or DataMart:

Derived FieldCalculation
Margin Variance (£)(Current Outturn Margin% × Current Value) − (Bid Margin% × Bid Value)
Margin Variance (%)Current Outturn Margin% − Bid Margin%
(Exact formulas may be adjusted based on Finance governance definitions.)

6.3 Recommended Additional Fields

These are not required for MVP but commonly expected in finance packs:

FieldReason
CustomerEnables customer-level analysis
Project ManagerSupports accountability and governance
Bid revenue / Bid costTransparency for margin calculations
Forecast revenue / Forecast costSupports audit and reconciliation
Project status (Active/Closed/On Hold)Essential for filtering
RAG or PMO status (if available)Adds context for risk
Reason for margin movementHelps commercial assurance

7. Data Sources

  • Project base data: IFS / Project core tables / CDM project_core
  • Bid values: Bid baseline stored in opportunity/project link or project baseline tables
  • Forecast values: Current forecast from project cost/revenue views (project_value, project_cost, project_revenue)
  • Dates: Project schedule or project_details view
  • PRU: Project organisational alignment via project or cost centre master data

(Exact table references will be confirmed during technical design.)


8. Business Rules

  1. Bid values and bid margin must come from the approved bid/baseline, not initial estimates.
  2. Forecast values must be the latest approved forecast (from project managers or financial planning data).
  3. Projects with no approved bid should be excluded or flagged.
  4. Suspended or dormant projects should be clearly labelled.
  5. Margin must use the Finance-approved formula for both bid and forecast.
  6. Where dates are missing or incorrect, the system should flag for review.

9. Functional Requirements

9.1 Report Outputs

  • Tabular view listing all projects and their bid vs forecast margin.
  • Ability to filter by PRU, Region, Customer, Project Manager.
  • Highlight projects with margin variance outside defined thresholds (e.g., >5% drop).
  • Export options (CSV, Excel, Power BI export).

9.2 Frequency

  • Refresh daily via Data Warehouse load (or as aligned with project forecast updates).

9.3 Security

  • Users must only see projects within their authorised region/PRU.
  • Finance users see all data; PMs see only their own projects.

10. Non-Functional Requirements

AreaRequirement
Data QualityMust use governed bid and forecast sources
PerformanceReport should load within 5 seconds for up to 5,000 projects
AuditabilitySource fields traceable to CDM views
ConsistencyMargin formulas aligned with Finance policies
MaintainabilityReport should use CDM-standard core & value views

11. Out-of-Scope Considerations for Future Iteration

  • Forecast time-phasing (monthly phasing).
  • Cashflow projections.
  • Risk-adjusted margin.
  • Integration with commentary capture.
  • Portfolio “drill-through” to invoices or timesheets.

12. Acceptance Criteria

The report is accepted when:

  1. All required fields (Section 6.1) are present and correct.
  2. Derived fields (Section 6.2) calculate consistently with Finance definitions.
  3. The report displays all active projects in the region.
  4. Margin variances are correctly highlighted.
  5. Access control meets Finance and Information Governance standards.
  6. Data from bid and forecast sources reconcile with period-end totals.

13. Delivery Plan (High Level)

  1. Dream – Confirm finance definitions (bid margin, forecast margin, variance).
  2. Discover – Map data sources from CDM views and IFS baseline/forecast tables.
  3. Develop _ Build CDM sub-view (project_margin_variance).
  4. Deliver – Develop Power BI / Reporting layer.
  5. Define & Document – Validate with Finance (two review cycles).
  6. Deploy to production.
  7. Monitor quality in first two periods.